Civic contract teams of Chennai Corporation have started work on relaying South Mada Street last night.
The road milling work which is of removing the top layer of the road to enable proper and standardised relaying has also been done.
But the milling has been done only for about 35mm while the street needs milling to be about 60 to 80mm, considering the street standard.
The GCC ‘s local area engineer has been informed of this need and he has promised this will be done.
The GCC has also been asked to consider milling and relaying all the mada streets in one go.